TOPOGRAPHIC, BATHYMETRIC AND LIDAR SURVEY FOR PROPOSED LNG JETTY - STA RITA POWER PLANT

CLIENT :

LOCATION:

DURATION:

PROJECT DETAILS:

SCOPE OF WORKS:

McConnell Dowell

Batangas City

December 2020 - January 2021

Survey for the Proposed LNG Jetty - First Gas Corporation

- Establishment of Ground Control Points
-Topographic Survey of the Perimeter Road going to LNG Jetty
- Bathymetric Survey of 30 Hectare Area using MultiBeam Echosounder and Sonar
- As-built Survey of Jetty PIles using Terrestrial Laser Scanner